Chancellor's Cabinet Report 11-17-26
Bond Measure HH Program Updates
Date: November 17, 2026
To: Chancellor’s Cabinet
From: Dr. Joel L. A. Peterson, Vice Chancellor & Executive Operations Officer
Subject: Bond Program Updates (November 2026)
Prior Week’s Key Accomplishments
City College
- Student Services & Administration (A) Building Air Handling Unit (AHU) Controls Upgrade: The project was approved on Nov. 10.
- Arts & Humanities Parking Structure (PS 300) Replace East Overhead Roll-Up: A notice of completion was sent on Nov. 10.
- “A” Building Expansion: A right-of-way (ROW) permit application for the Bloom Energy yard relocation was submitted to the City of San Diego on Nov. 10. Increment 1 and plans for the temporary campus bookstore swing space in MS-123 were submitted to Division of the State Architect (DSA) on Nov. 10. A Design Development (DD) comment review session was held on Nov. 13.
- Business and Technology (BT) Building Restrooms: Construction began Nov. 11.
Mesa College
- Performing Arts Center / Administration & Parking Structure: Electrical and low-voltage design-assist partner evaluations were received on Nov. 9 and remained under district review. A chemical and hazardous materials storage meeting was held on Nov. 11.
- Design Center Improvements: A follow-up meeting to coordinate moves and logistics was held on Nov. 11.
- English/Student Support Building: A programming check-in meeting with the Design-Build Entity (DBE) was held on Nov. 11.
- Athletics Complex: A chemical and hazardous materials storage meeting was held on Nov. 11. A DD workshop with campus leadership focused on site plans and exterior and interior materials was held on Nov. 12. A meeting with the DBE to discuss future commencement and convocation activities in the new facilities was held on Nov. 13.
- Learning Resource Center (LRC) Radio Frequency Identification (RFID) Gates Replacement: A job walk and site survey with the contractor and vendor was held on Nov. 12.
Miramar College
- Performing Arts Center & English/Gallery Building: The district completed its review of the 100% DD deliverable on Nov. 9.
- Aviation Instructional Center: The DBE continued developing three design options for the alternative site during the week of Nov. 9.
- Early Education Center: A construction kickoff meeting with the DBE was held on Nov. 9, followed by a meeting with campus leadership and stakeholders to discuss graphics and signage on Nov. 10.
- Pool Deck Replacement and Replaster: Bids were received on Nov. 13.
College of Continuing Education
- Educational Cultural Complex (ECC) Ceramics Renovation: A landscape site walk was held on Nov. 10.
- ECC Main Sanitary Sewer Replacement: The new project was approved on Nov. 10.
- New Site for SDCCE: A stakeholder design meeting was held on Nov. 10.
- CE Mesa Building Improvements: A design presentation to the Executive Presidents Committee (EPC) was held on Nov. 10.
- Lighting Inverter and Batteries Replacement: The project is scheduled for Board approval on Nov. 12.
- Harbor View L1 East Door Security Monitoring: A site walk with JJJ Enterprises was held on Nov. 12, to evaluate existing conditions.
- ECC Room C120 Accessibility & Safety Improvements: A contractor site walk was held on Nov. 12 with JJJ Enterprises to coordinate the emergency panic button installation and ASSA ABLOY to coordinate the automatic door operator installation.
- West City Expansion: A pre-application meeting with DSA was held on Nov. 12.
- ECC Welding: An equipment coordination meeting with stakeholders was held on Nov. 13.
Other District Locations
No items to report.
Coming Week Look-Ahead
City College
- “A” Building Expansion: A security systems site visit at the Building D bookstore is scheduled for Nov. 16 to support swing space preparations. An on-site bookstore relocation assessment with JE Moore and a presentation to the college president is scheduled for Nov. 17. A site logistics planning meeting is scheduled for Nov. 20.
- Saville Theatre: Fault line investigation and trenching in the landscaped area west of the LRC building will continue through Nov. 24.
Mesa College
- Athletics Complex: The DBE is scheduled to submit the 50% DD deliverable during the week of Nov. 16. An initial review of the deliverable with the DBE is scheduled for Nov. 17, followed by a cost estimate presentation to the district on Nov. 18. A value engineering session with the DBE is scheduled for Nov. 20.
- Mesa Commons Envelope Leak Mitigation: A pre-construction meeting with campus stakeholders is scheduled for Nov. 18
- English/Student Support Building: A meeting with the steering committee is scheduled for Nov. 18 to present programming workshop findings.
- Performing Arts Center / Administration & Parking Structure: The DBE is scheduled to submit the 100% DD package during the week of Nov. 16, with stakeholder review meetings scheduled for Nov. 17-20.
Miramar College
- Heavy Duty Advanced Transportation (C3) Building Roll-Up Door Motor Replacement: A punch-list and acceptance walk is scheduled for Nov. 16.
- Aviation Instructional Center: The architect is expected to review and provide comments on the survey drawing for the potential alternative site during the week of Nov. 16.
- Early Education Center: A design completion meeting with the DBE and stakeholders is scheduled for Nov. 18.
- Performing Arts Center & English/Gallery Building: A DD completion meeting with the DBE and stakeholders is scheduled for Nov. 19.
- Pool Deck Replacement and Replaster: The final agenda item for the December Board meeting is due by Nov. 19.
- Arts & Humanities (H), Business & Math Buildings (M), Science (S5), Campus Police (T1), Roof Replacements and Diesel Technology (C1), Learning Resource Center (LRC) Buildings Gutters: Roof punch-list work and manufacturer warranty inspections for buildings H and M are targeted for completion by Nov. 20.
College of Continuing Education
- ECC New Facilities Building: A stakeholder design meeting is scheduled for Nov. 20.
- West City Expansion: A stakeholder design meeting is scheduled for Nov. 16
Other District Locations
No items to report.
Key Items of Interest
No items to report.
Upcoming Needed Campus Action Items (Time Sensitive)
No items to report.